Track Record
Project Experience
AXYCAD delivers reinforced concrete packages and civil engineering works across transport, highways, water and utilities, energy, data centres, industrial and building sectors. Our leadership and delivery team bring close to two decades of hands-on experience managing complex RC programmes on major UK infrastructure — from HS2 viaducts and highway flyovers to settlement tanks, substation foundations and commercial builds. The specialist reinforcement, formwork and concrete teams who delivered those projects now form part of AXYCAD's operational model.

3 abutments and 55 piers forming the substructure of a major viaduct. High-volume reinforced concrete programme requiring proprietary formwork cycling, large continuous pours and full ITP documentation.
What was delivered
- High-volume RC works across abutments and 55 piers
- Proprietary formwork cycled across 55 pier locations
- Large-volume continuous pours (up to 1,512 m³)
- Full ITP pack and handover documentation

Multi-structure FRC package covering overbridges, culverts, a footbridge and a full underpass. Full reinforced concrete delivery with temporary works design, commercial management and structured handover across all structures.
What was delivered
- Full lifecycle FRC delivery across multiple structures
- 36+ TWD packages designed and managed
- Scope expansion absorbed without programme disruption
- Design changes integrated through live programme
- Underpass delivery within expanded package

Full FRC package covering both abutments, wing walls at 4 corners, piers, deck with precast beams and associated culvert works. Achieved GOOD safety rating on completion.
What was delivered
- Full FRC across both abutments and wing walls
- Wing wall pile cap construction at all 4 corners
- Pier construction and deck with precast beams
- Culvert works delivered within the same package
- Crane operations and edge protection managed throughout

Full FRC package for a flyover structure on a live carriageway carrying over 10,000 vehicles per day, plus 1,000 m RECO retaining wall (2,672 panels) awarded separately on the strength of delivery performance. Concrete works executed within single night road closures using bespoke temporary works designs and own shuttering systems.
What was delivered
- Full FRC package on live carriageway with night closures
- 1,000 m RECO wall — 2,672 panels, 57,478t imported material
- Bespoke TWD and own shuttering systems throughout
- Bridge bearing installation and beam supervision added to scope
- Programme reduced — time and cost savings delivered
- Zero inert waste to landfill through early waste stream planning

2No FSTs — hoppers, base slabs and ring beams. 300 mm slabs at 7.5°, conical hopper formwork, radial rebar layout and metal waterstop installation.
What was delivered
- 2No circular FSTs constructed in cofferdams
- Bespoke timber formwork for conical hoppers
- Radial rebar layout and fixing
- Concrete placement to sloping bases
- Metal waterstop installation
- Ring beam completion

1No PST — hopper, base slab, ring beam and mass concrete benching. 5 sequenced pours with pre-fabricated cylinder formwork crane-installed on site.
What was delivered
- Pre-fabricated formwork crane-installed on site
- Steel fixing in planned sequence
- 5 sequenced concrete pours
- Radius edge formwork for curved elements
- Integration with precast wall panels
Sectors
